Illustrative image – not actual.GAIL India's Rs.7,000 crore petrochemical complex at Kochi has been shelved for the time being due to technical issues.
The project had to be shelved as the Kochi LNG terminal will get only lean LNG, which is not suitable for the proposed gas cracker unit. The proposed Kochi LNG terminal of Petronet LNG has been delayed by almost two years, according to the revised schedule.
It is learnt that the terminal will start by February 2011, earlier it was scheduled to be commissioned by 2009. Petronet LNG will sign an agreement with Gorkhaon Gas of Australia by mid-July 2008, for supplying 2.5 million tpa LNG on an yearly basis and will also reach an agreement with NTPC for selling a major chunk of gas from the terminal.
Also, the package for the awarding the EPC (engineering, procurement and construction) contract for the project had to be re-designed because of the soil condition in the project area. The contract isnow expected to be awarded by July-August 2007.
Also See:
Bhoomi poojan performed for Kochi LNG terminal (30-Jan-07)
Related Links:
Project profile