Illustrative image – not actual.GAIL India is planning to invest Rs.45,000 crore by 2011 from the present Rs.16,000 crore for laying of seven new pipelines.
The seven new pipelines, involving an expenditure of a total of Rs.18,000 crore will increase GAIL's network to 11,500 km from the present 6,700 km doubling the carrying capacity to more than 280 square cubic metre a day.
To be executed in the first phase by 2009, government approval has been received for four pipelines - the 610-km Dadri-Bawana-Nangal pipeline passing through UP, Delhi, Haryana and Punjab, the 310 km Chainsa-Gurgaon-Jhajjhar-HIssar pipeline through Haryana and Rajasthan, the 876-km Jagdishpur-Haldia pipline through West Bengal, Jharkhand, Bihar and UP and the 730 km Dabhol-Bangalore pipeline through Haryana and Rajasthan.
Plans were afoot for augmenting the capacities of three existing pipelines--the Dahej-Vijaipur pipline, the Vijaipur-Dadri pipeline and the Vijaipur-Auraiya-Jagdishpur pipeline in the second phase by 2011.
To ensure gas availability, GAIL has already signed memorandum of understanding (MoU) with Reliance Industries and ONGC for transportation of natural gas from various gas sources. It also signed a pact with Shell India for sharing of GAIL's pipeline interconnectivity with Hazira terminal for gas supplies in the country.
Also See:
Gail to invest Rs.18,000 crore in gas pipeline projects (31-Mar-07)