GAIL India has reconfigured the Rs 12,000 crore Jagdishpur-Haldia pipeline, which will connect Varanasi to the gas grid, to link the Dhamra terminal.
The over 2,500-km line will be constructed in three phases and will also now connect Dhamra LNG import terminal in Odisha.
In the first phase, a trunk pipeline from Phulpur (Allahabad) will be laid to Dobhi (Gaya) in Bihar with spur lines to Barauni and Patna. The 755-km Phase-I project will cost Rs 3,200 crore and will be completed by December 2018.
The Phase-I project will supply gas to major industries such as the Barauni Refinery and the Barauni fertilizer plant, which is being revived, besides power and steel plants. It will also help in setting up of City Gas Networks in major cities enroute.
In Phase-II, a 1200-km line would be laid from Dobhi to Bokaro/Ranchi in Jharkhand and Angul and Dharma in Odisha at the cost of Rs 5,565 crore. Phase-III will involve laying a 583-km line to Haldia at the cost of Rs 3,425 crore.