Illustrative image – not actual.GAIL proposes to set up three new
LPG plants in South India at an estimated cost of Rs.810 crore so as to use the
excess gas available in the Cauvery and Krishna-Godavari basins. The
feasibility studies for all the plants were being commissioned.
GAIL proposes to set up a LPG
plant at Tirumakkottai in Tamil Nadu at an estimated cost of Rs.160 crore. This
plant would use gas available from the Cauvery basin. The plant would have a
capacity of two million metric cubic metres of gas per day. GAIL proposed its
second plant at Tatipaka in Karnataka with a capacity of eight million metric
cubic metres of gas per day. The cost of this plant was estimated at Rs.490
crore. The plant would be capable of producing 96,000 tonne of LPG and 36,500
tonne of other liquids annually. The third plant was also proposed near the
Krishna-Godavari basin at Surya Saynam at an estimated cost of Rs.160 crore.
This plant would have a capacity to produce 55,000 tonne of LPG and 27,200
tonne of other liquids.
GAIL planned to increase its gas
supply from the present 60 to 143 million metric cubic metres of gas per day
over the next five years. For this purpose it planned to use the additional gas
available from the domestic sources. These sources include Tapti oil fields and
the proposed LNG terminals to be set up by Petronet LNG, Trombay LNG, Pipavav,
Hazira, Dabhol and Kakinada.