GAIL places order for steel pipesIllustrative image – not actual.

GAIL India has placed orders for purchase of 315 km steel pipes to carry fuel to shut fertiliser plants in Bihar.

To ensure energy security for the Gorakhpur, Barauni and Sindri fertiliser plants under revival enroute Phulpur-Haldia natural gas pipeline, GAIL has placed orders for purchase of 315 km of line pipes for Auraiya-Phulpur pipeline with Jindal Saw and Essar Steel at a total cost of Rs 305 crore.

The sections for which the pipeline procurement have been placed are being taken up for revival of shut fertiliser plants at Gorakhpur, Barauni and Sindhri.

Tenders for laying works of Auraiya-Phulpur pipeline and for procurement of line pipes of Gorakhpur spurline have already been floated.

The company is planning to start the construction work in these sections from October 2016.

The 315 km Auraiya-Phulpur pipeline, 341 km Phulpur-Dobhi (Gaya) section, and 414 km spurlines to Gorakhpur, Varanasi, Patna and Barauni will be completed by December 2018, at a cost of Rs 4,600 crore.

Phase-II (1,201 km) and Phase-III (583 km) of the Phulpur-Haldia pipeline project are targeted to be completed by December 2019 and December 2020 at an estimated investment of Rs 5,565 crore and Rs 3,425 crore respectively.







 