GAIL (India) to add 5,500 km gas pipeline network in next three yearsIllustrative image – not actual.

GAIL (India), a natural gas processing and distribution company, is planning to construct 5,500 km of new gas pipeline in the next three years. The company aims to augment its gas pipeline network by around 50 percent.

The company is looking to set up 400 CNG stations and giving out a record 10 lakh piped natural gas (PNG) connections to household kitchens. The capacity addition will be developed in phases.

GAIL is constructing 2,655 km gas pipeline from Jagdishpur in Uttar Pradesh to West Bengal and Odisha. Phase-I of the project will be completed before the scheduled target of December 2018.

Jagdishpur-Haldia and Bokaro-Dhamra Natural Gas Pipeline (JHBDPL) project which is also known as the Pradhan Mantri Urja Ganga project, was inaugurated in July 2015.

The pipeline section from Phulpur to Varanasi has been commissioned, while the section to Patna will begin in the next couple of months. The gas pipeline will be extended to Guwahati by laying an additional 750 km line.

The proposed gas pipeline up to Guwahati will interconnect with the upcoming 1,500 km Indradhanush pipeline network.

Moreover, the gas supplies through city gas distribution (CGD) networks have commenced at Bhubaneswar and Cuttack.

 