Illustrative image – not actual.GAIL (India), successfully commissioned the Dabhol LNG terminal at Ratnagiri, Maharashtra around 340 km south of Mumbai.
The terminal is operated by RGPPL, a JV of GAIL (India) and NTPC as major share-holders and remaining equity being held by financial institutions and MSEB. It will serve as a gateway for entry of natural gas to the southern and western parts of the country. GAIL, the commercial operator of the terminal, had arranged commissioning cargo for the terminal in December 2012.
The commissioning of the Dhabol regas terminal provides access to natural gas supply to the southern and western states - Maharashtra, Goa, Karnataka and Tamil Nadu. The current capacity of the LNG terminal is 5 million tpa. GAIL is likely to expand the capacity up to 7.5 million tpa and then to 10 million tpa in a phased manner by next 2-3 years. It has under-written the re-gas capacity of the facility for 25 years for lending support to the project. GAIL is also at an advanced stage of commissioning the 1400- km Dhabol-Bangalore pipeline system. In the immediate future, the re-gas from the terminal will cater to the demand of the customers in Maharashtra through GAIL's Dabhol-Panvel pipeline connected to Maharashtra regional pipeline network.
Related Link:
Project profile