GACL plans cement capacity addition at ChandrapurIllustrative image – not actual.

Gujarat Ambuja Cements plans to increase the capacity of its Chandrapur plant from 2 million tonnes to 2.5 million tonnes and augment its power generation capacity with an investment of Rs.40 crore. The investment would be made over a period of one year. According to company officials, some investments have already been made for increasing the captive power generation capacity.

 

As of April 2002, the company was getting the third turbine operational and commercial production of cement was to begin soon.

 

The Chandrapur plant was set up at a cost of Rs.625 crore with additional expenditure incurred on other infrastructure such as railway sidings and water pipelines. The Chandrapur plant will cater to the Maharashtra (except Mumbai) and Andhra Pradesh market. Earlier, GACL had planned setting up a cement plant at Guntur district of Andhra Pradesh, however, the project had to be deferred due to the poor demand situation in the Southern markets.