G R Infraprojects gets provisional completion certificate for Purvanchal ExpresswayIllustrative image – not actual.
G R Infraprojects has received provisional completion certificate for Purvanchal Expressway (Package-VII). 
 
The project involves development of Purvanchal Expressway (Package-VII) from Mojrapur (Azamgarh district) to Bijaura (Ghazipur district) (246.500 km to 292.530 km) in the state of Uttar Pradesh on EPC basis. 
 
The project has been provisionally completed. The provisional completion certificate has been issued by the Independent Engineer on 23 December 2021 and has declared the project fit for entry into commercial operation with effect from 15 December 2021. 
 
The contract price of the project is Rs 1,437.47 crore. The schedule completion date is 7 March 2022.