Multinational equipment manufacturer, Fuller, has picked up a 14 per cent stake in the 2.6 million tonne cement project being implemented by Sanghi Cements Ltd, part of the Sanghi group of companies. Through its affiliates, Fuller India and Fuller International, Fuller has picked up this stake for a consideration of Rs.26 crore.
The cement project, coming up at Gujarat, has recently achieved financial closure. The total cost of the project that was Rs.850 crore at the time of conception has risen to Rs.1,200 crore following delays in project implementation. The project has been funded by financial institution lending to the tune of Rs.770 crore, issuance of preference shares worth Rs.260 crore and the rest through equity.
The cement unit would also have a captive power plant of 45 MW and a jetty to facilitate transport.
It is expected that the unit would start clinker production by April 2001 and cement production would start sometime in July 2001.
On commissioning of the project, the total cement capacity in Gujarat would rise to around 15 million tonnes. Against this, the official demand for cement in the State is only around 5.5 million tonnes. Excess cement produced in Gujarat is usually sold to Maharashtra, Kerala and Rajasthan.