Illustrative image – not actual.Fuelco Power & Mining is progressing with land acquisition for its proposed 200 MW coal-based power project in Chandrapur district of Maharashtra. Company officials told ProjectsToday that out of 150 acres that the project would need; some 50 acres have been acquired so far. The balance will be acquired by February 2007.
The company is awaiting coal allotment from the Union government and also environmental clearance. The project will be implemented through the EPC route and tenders will be floated after all approvals are in place. The detailed project report was completed in June 2006.
The project is coming up in two phases. In Phase I, a 50 MW power plant costing Rs.149 crore will be set up followed by a 150 MW plant with an investment of Rs.460 crore.