Illustrative image – not actual.On November 29, 2002, the Chairman and Managing Director of the Andhra Pradesh Generation Corporation (APGenco), Mr J. Parathasarathy, commissioned the fourth unit
of the underground, 6X150 MW hydro power station, on the left bank of the Srisailam reservoir.
The Rs.2620 crore project, located 250 meters below the ground level in the midst of Rajiv Tiger Reserve Forest, is being funded by the Japanese Bank for International Cooperation to the extent of Rs 2,022.69 crore. The balance amount is being supplied by APGenco.
The commissioning of the fourth unit has rendered APGenco the third biggest public sector power generating utility, the first two utilities being NTPC and MSEB. The installed capacity of the hydro power stations of APGenco goes up to 3282 MW and its total installed power capacity will increase to 6247 MW.
It may be noted that APGenco's installed capacity till date forms about 62.4 per cent of the total capacity of 10,000 MW of Andhra Pradesh Power System.
The company intends to commission the remaining two units of the hydro power station in 2003.
The power station with reversible type pump turbine motor generating units would facilitate mopping up of surplus off-peak thermal power in the system to supply power during the peak hours. It would also generate cheap conventional energy with monsoon surplus flows in the river. Stabilisation of the grid and improving voltage would be the additional advantages.
Reportedly, the power generation at the project, to a certain extent, is dependent on the water level in the downstream Nagarjunasagar Dam. Studies are under way to find the exact extent of river course correction needed for pump mode operation. In a pump mode operation, water would be pumped up into the reservoir so as to utilise it for generation of electricity.
APGenco would reportedly be in a position to undertake full-fledged pump mode operation by 2007-08.