Illustrative image – not actual.During the first 2 quarters of 2002-03, the Centre approved projects worth Rs.8, 484 crore for upgradation of the power transmission and distribution system across states under the Accelerated Power Development and Reforms Programme (APDRP).
The major part of the investment will be made in Andhra Pradesh, Rajasthan, Maharashtra and Karnataka. They together account for 43 per cent of the amount sanctioned in the 2 quarters.
In July, projects worth Rs.4,500 crore was approved and in September 2002, an additional Rs.3,984 crore was approved for systems upgradation in 63 cities. The bifurcation is as follows:
|
States |
Approved DPR
cost July
2002 |
Approved DPR
cost Sept.
2002 |
|
Karnataka
|
440 |
720 |
|
Andhra
Pradesh |
609 |
365 |
|
Rajasthan |
489 |
424 |
|
Maharashtra |
103 |
516 |
|
Madhya
Pradesh |
371 |
- |
|
Haryana |
335 |
- |
|
Gujarat |
358 |
329 |
|
Delhi |
- |
488 |
|
Total |
4500 |
3984 |
The approval of the funding is based on detailed project reports for circles identified by states. For the 63 cirlces selected in the first phase, the central public sector undertakings viz. the National Thermal Power Corporation and Powergrid are working out various measures with respective state organizations. To avail of funds for the programme, the state will have to fulfill the norms laid in the memorandum of understanding signed with the Union Power Ministry stipulating time-bound reform measures.