Four LPG bottling plants to come up in KarnatakaIllustrative image – not actual.

Bharat Petroleum Corporation (BPCL) and Indian Oil Corporation (IOC) plan to set up 4 LPG bottling plants in Karnataka.

 

BPCL would be setting up a bottling plant at Bangalore with an investment of Rs.30 crore. Presently, the company is in talks with the state government for acquiring 40 acres of land for the project. The acquisition process is expected to be completed by the end of July 2002 and the project is expected to be ready within 18 months.

 

IOC also plans to set up a LPG bottling plant at Shimoga with an investment of Rs.29 crore. This plant would go on stream from October 2003.

 

IOC also plans to set up 2 more such plants at Gulbarga and Desur. These plants are estimated to cost Rs.25 crore and Rs.21 crore, respectively. Of these the Gulbarga plant is expected to be ready by September 2004.

← All latest storiesBack to top →