The Cabinet Committee on Economic Affairs (CCEA) in 2017 had approved the development of Porbandar-Dwarka on NH-8E (Ext) in Gujarat.

G R Infraprojects, the concessionaire for Porbandar Dwarka Expressway, was assigned the task of developing the 118 km highway.

The project involved four-laning with paved shoulder of Porbandar-Dwarka section from 356.76 km (design chainage 379.10 km) to 473.00 km (design chainage 496.84 km) on PPP basis through HAM mode.

In 2018, work on constructing the highway commenced and around 86 percent of land was acquired. Projects Today has learnt that around 36 percent work has been effectively finished at the beginning of December 2018.

The four-laning of Porbandar-Dwarka road project, being developed at an estimated cost of Rs 1,600 crore, is set for completion in August 2019.