Four cos bid for consultancy tenderIllustrative image – not actual.
Four companies have placed bids for the consultancy tender for a cable stay bridge connecting Ghansoli to Airoli. The stretch will be 1.95 km long and 34 mtr wide. The Navi Mumbai Municipal Corporation (NMMC) will construct this cable bridge as part of the Palm Beach road extension project.

The stretch between Belapur and Koprigaon of 12 km and the one between Ghansoli and Airoli of 4 km have been completed by CIDCO. The estimated cost of bridge is Rs 700 crore. The work will be completed in two years after the tender for construction is awarded.

The last date for filing the tender was 30 May, 2017. The scope of work involves design, planning and management of the bridge, and a detailed study of the technical and financial viability of the project.

The successful bidder will be given around nine months for aerial survey, site inspection, soil testing, design, making tender documents for the construction, project management consultancy, getting environment nod, and procuring NOC from the Maharashtra Coastal Zone Management Authorities.

← All latest storiesBack to top →