Illustrative image – not actual.Oommen Chandy, Chief Minister of Kerala, is likely to lay the foundation stone for a new terminal of the Cochin International Airport on 2 February, 2014.
The construction of the new terminal will entail an investment of Rs 800 crore. The 1.5 million sq ft terminal is expected to be completed within 30 months. It will have the capacity to handle 4,000 passengers in an hour.
The construction work for the project will be executed by Larsen & Toubro. The terminal with two levels will have provision for 112 check-in counters, in-line baggage screening facilities, 100 immigration counters, duty free shops of 30,000 sq ft at departure and arrival lounges, 19 boarding gates, 15 aero bridges, six baggage conveyer belts, and fully covered alighting and boarding areas.