Foundation stone to be laid for IISCO's expansion programmeIllustrative image – not actual.

On 24 December 2006, Prime Minister of India, Dr. Manmohan Singh laid the foundation stone for Burnpur-based IISCO Steel Plant's modernisation and expansion programme. The project will entail an investment of Rs.9,592 crore.

The major facilities to be installed under the modernisation package includes a 7 mmetre tall coke oven battery, two sinter machines, new blast furnace, three 150 tonne convertors, two 6 strand billet casters and one four strand beam blank/bloom caster. A new universal section mill of 0.6 million tpa capacity and a new wire rod and a bar mill of 1.2 million tpa capacity will also be included in the expansion programme.

The expansion project is an integral part of SAIL's growth plan to produce 23 million tpa of hot metal by 2010. At present, ISP's capacity stands at 4.26 lakh tpa of saleable steel, mainly structurals and bars and rods and also produces 2.54 lakh tpa pig iron.

Also See:

SAIL approves three modernisation projects (30-Aug-06)

← All latest storiesBack to top →