Illustrative image – not actual.Foundation stone for the Rs.5,985 crore Upper Bhadra lift irrigation project is scheduled to be laid in October 2008.
The tendering process had been completed for the Phase I and II of the irrigation project. For Phase I, Rs.3,388 crore will be invested to pump water from the Tunga to the Bhadra river and Rs.2,597 will be spent for constructing canals.
Sew-Jyoti JV has obtained the tender for Phase I and Bangalore based SNC Power Corporation has bagged tender for Phase II.
Also See:
Karnataka Cabinet clears Upper Bhadra lift irrigation project (28-Aug-08)
Addendum:
Foundation stone for the Rs.5,985 crore Upper Bhadra lift irrigation project was laid on 09 February 2009.