Illustrative image – not actual.On 7 February 2003, Rashtriya Ispat Nigam laid the foundation stone for the fourth coke oven battery project. The project, which would entail an investment of Rs.320 crore, would pave the way for capacity expansion.
The project, which would reportedly expand the capacity from 3 million tonne to 5 million tonne, is expected to be completed in around 30 months period.
The project
would be funded out of RINL’s internal resources.
The Steel Ministry has agreed in principle to extend a loan of Rs.250 crore to divert Godavari waters through the Yeleru canal to the plant. RINL and the other units would make use of 2.5 tmc feet of water while the rest would be given to the Vizag corporation. The Andhra Pradesh Industrial Infrastructure Corporation was the nodal agency.