Illustrative image – not actual.The Union Minister for Power, Mr Suresh Prabhu would be laying the foundation stone for the Ramagundam III Transmission System in Andhra Pradesh on 23 February 2002.
The cost of the project is estimated at Rs.390 crore
and is scheduled for commissioning in 2004-05. The project would be funded by a
loan from Asian Development Bank.
The transmission system comprises:
Ø
Ramagundam – Hyderabad 400 kV D/C (200 km)
Ø
Hyderabad - Kurnool – Gooty 400 kV S/C (300 km)
Ø
Gooty – Nelamangala 400 kV S/C (250 km)
Ø
Khammam – Nagarjunasagar 400 kV S/C (150 km)
The project would strengthen and improve reliability of the existing trunk transmission corridor between Ramagundam and Bangalore / Chennai by providing an alternate path. It would also provide a reliable power source to Hyderabad, which is the most promising load centre in the southern region.