Illustrative image – not actual.On 30 August 2009, K Sankaranarayanan, Jharkhand Governor, laid the foundation stone for the 48 million ltrs per day drinking water supply project in Jamshedpur under the Mango Notified Area Committee (MNAC).
Jamshedpur Utilities & Services Company (JUSCO) has reportedly bagged the proposed project from the Jharkhand Government. JUSCO, which had earlier won the project based on an open tender basis, has been issued the Rs 64.18 crore work order from the state government.
The revised administrative approval to the scheme, to be completed within the next 24 months, was accorded by the Department of Urban Development, Jharkhand on 24 August 2009. It involves operation and maintenance of the project for six months from the date of completion.
The Mango urban water supply re-organisation scheme involves construction of four ground water reservoirs, four water towers, supply and laying of 4.15 km of raw water mains, supply and laying of 7.8 km of clear water mains and of a 148-km distribution network.
The work also requires JUSCO to survey, design and construct a water treatment plant complete with civil, mechanical & electrical works on a turnkey basis including six months of operation and maintenance.