Foundation stone laid for Krishna water-III schemeIllustrative image – not actual.

N Kiran Kumar Reddy, Chief Minister of Andhra Pradesh, has laid the foundation stone for Phase-III of the Krishna Drinking Water Supply Project in Hyderabad.

 

The project is being executed by Hyderabad Metropolitan Water Supply and Sewerage Board (HMWS&SB) with an investment of Rs 1,800 crore, near Vanasthalipuram on the city outskirts. The main components of the project are construction of a water treatment plant (WTP) with 90 million gallons per day capacity, clear water and balancing reservoirs with 117 million ltr capacity to facilitate intermediate pumping, construction of pump houses, and erection of pumping equipment.

 

It also includes laying of clear water transmission mains of 113.5 km length, and laying of distribution trunk mains of 62 km length to connect the service reservoirs

 