Illustrative image – not actual.Recently, works had been launched to link the rivers Godavari and Penna at an estimated cost of Rs 83,796 crore in five phases. Phase-I will cost Rs 6,020.15 crore. The Chief Minister said 65 percent of the works on the mega Polavaram project on Godavari had been completed and all efforts will be made to give water by gravitational flow by May 2019, and to complete the project by 2018-end.
In Phase-I, 8,500 cusecs of water from Pattiseema and 6,870 cusecs of water from Chintalapudi lift will be taken to Prakasam barrage on the Krishna at Vijayawada. From Prakasam barrage, 7,000 cusecs of water will be carried to the Nagarjuna Sagar right main canal in five phases by laying 10.25 km of pipeline from the Krishna and gravity canal at a stretch of 56.35 km using five lifts.
Godavari waters will be brought up to Nakirekallu, and a linkage will then be established with the Sagar right main canal, resulting in assured irrigation to over 9,61,000 acre in Guntur and Prakasam districts.