Illustrative image – not actual.Union Power
Minister, Mr Suresh Prabhu laid the foundation stone of the Stage III 500 MW
Ramagundam Super Thermal Power Station (RSTPS) on 11 January 2001. The project
is being implemented at Ramagundam in Andhra Pradesh.
The unit,
expected to cost Rs.1,818 crore, would be commissioned by 2004-05. It would be
the seventh unit of RSTPS, which currently has a capacity of 2,100 MW.
The new unit
would have a debt-equity of 70:30 with the entire equity being brought in by
NTPC through its internal accruals.
NTPC currently
has a capacity of 19,345 MW and accounts for over 25 per cent of the total
power capacity in the country. NTPC has
set a target of achieving a capacity of 40,000 MW by the year 2012. NTPC has 19
power project on hand of which two are under construction. These are the 1,000
MW Simhadri Power Project in Andhra Pradesh and the 2,000 MW Talcher II Power
Project in Orissa.