Illustrative image – not actual.Rajasthan Chief Minister , Ms. Vasundhara Raje, is scheduled to lay the foundation stone on 9 December 2005 for Rajasthan Vidyut Utpadan Nigam's Chhabra power plant in the state.
The 500 MW coal-based power project, coming up in Chowki Motipura area near Kawai in Baran district, will entail an investment of Rs.1,750 crore.
The power plant having two units of 250 MW each will be spread over 523 ha of land. The site for the project had already been identified in January 2005. TCE Consulting Engineers is rendering project consultancy.
The Rajasthan government will fund 10 per cent (Rs.175 crore) of the total project cost, and the remaining amount of Rs.1,575 crore will be raised from financial institutions in the form of loan. The state government has already made a provision of Rs.55 crore in the budget for 2005-06 to meet the initial cost of the power project.
The power unit will need 2.6 million tonnes of coal and 800 million cubic feet of water a year in the first phase. The state government has initiated the process to meet the demand.
Unit 1 is scheduled for completion by September 2008, while Unit 2 will be commissioned in December 2008. Once completed, the power project is expected to contribute 12 million kwh of electricity per day to the state power grid.
Background: The above-mentioned project represents Phase I of the 1,000 MW Chhabra project for which RVUNL had invited bids for comprehensive EIA studies, soil investigation studies and preparation of DPRs, in August 2005. Click here for tender details.