On 24 June 2006, Prime Minister, Dr.Manmohan Singh laid the foundation stone for ten -lane mixed corridor from Silk Board Junction to Electronic City on the Bangalore-Hosur section on NH-7.

The scope of work includes improvement of the highway between 8.765 km and 33.13 km, involving construction of a nine km four-lane elevated highway from Silk Road Junction to Electronic City.

The works that will be completed during the period are as follows:

  • Construction of an elevated 4-lane highway from 9.5 km to 18.75 km including Electronic City interchange
  • Widening of ground level existing road from 8.765 km to 18.75 km to provide wide carriageways for 8.75 km in each direction
  • Construction of pre-cast RCC-covered drains on both sides of main carriageways after dismantling existing drains.
  • Widening of cross drainage structures
  • Construction of pedestrian underpasses at Bommana Halli (9.925 km), Garvebavi Palya (11.385 km), Kudlu Gate (12.140 km) and Singasandra (13.550 km)