Illustrative image – not actual.Nearly 40 percent work has been completed on Selander Bridge project in Dar es Salaam, Tanzania. The project is worth USD 112.8 million.
The work on the bridge is being undertaken by the Tanzania National Roads Agency (TANROADS). The groundbreaking ceremony for the project was performed in 2018.
The bridge will be ready for operations by June 2021, four months before the official completion date, because the remaining work is not as challenging as the completed one, and suspension of flights in foreign countries will be lifted soon.
The new bridge is funded jointly by the government of South Korea at 82.9 percent of the entire cost, and the government of the Republic of Tanzania. It connects the roads linking Aga Khan Hospital and Coco beach and measures approximately 6.23 km.
With 180 tonne capacity, the bridge is expected to ferry 55,000 vehicles or its whereabouts per day. This is expected to significantly reduce congestion along the overwhelmed independence-time Selander Bridge.
The work on the bridge is being undertaken by the Tanzania National Roads Agency (TANROADS). The groundbreaking ceremony for the project was performed in 2018.
The bridge will be ready for operations by June 2021, four months before the official completion date, because the remaining work is not as challenging as the completed one, and suspension of flights in foreign countries will be lifted soon.
The new bridge is funded jointly by the government of South Korea at 82.9 percent of the entire cost, and the government of the Republic of Tanzania. It connects the roads linking Aga Khan Hospital and Coco beach and measures approximately 6.23 km.
With 180 tonne capacity, the bridge is expected to ferry 55,000 vehicles or its whereabouts per day. This is expected to significantly reduce congestion along the overwhelmed independence-time Selander Bridge.