Forty-five percent tunnelling work completed for Mumbai Metro-3Illustrative image – not actual.

The Mumbai Metro Rail Corporation (MMRCL) has completed 45 percent tunneling work on Metro-3 (Colaba-Bandra-SEEPZ). MMRCL has achieved tunneling breakthrough on nine out of 32 tunnels till the end of March 2019.

The project is being built at a cost of Rs 24,500 crore, the 33.5 km Mumbai Metro-3 corridor is expected to ease travelling woes by connecting the island city to western suburbs.

Phase-I of the corridor -- from Aarey to Bandra-Kurla Complex (BKC) -- is likely to be operational by 2021. Phase-II is from BKC to Cuffe Parade. MMRCL has deployed 17 tunnel-boring machines in the city for the job, which have so far excavated 31 lakh tonne of earth.

The tunnelling work for Metro-3 corridor has been divided into seven packages to complete the sections simultaneously and work has started on all of them. In March 2019, the tunnel boring machine Godavari-1 covered a distance of 2.9 km at the domestic airport Metro station. The breakthrough was achieved in 455 days.

← All latest storiesBack to top →