FIs ask Vidarbha Power to sign PPA before any further fundingIllustrative image – not actual.

Financial institutions, led by ICICI, have asked the Lloyds promoted Vidarbha Power Company (VPC) to sign a power purchase agreement (PPA) with Maharashtra State Electricity Board as a pre-condition to further funding the power project.

 

VPC, which is reportedly facing an acute fund shortage is setting up 80 MW, coal based power project in Wardha, Maharashtra. The power project, which is about half complete, is behind schedule.

 

Initially, the project was conceived as a captive power plant. However, as part of a restructuring plan, it was hived off into a separate company, VPC. This power project is expected to reduce cost of power for Lloyds Steel Industries Ltd, which presently buys power at Rs.4 per unit.