First unit of Mundra UMPP may commission by SeptemberIllustrative image – not actual.

Coastal Gujarat Power, the SPV floated by Tata Power, is likely to commission the first 800-MW unit of the 4,000 MW UMPP at Mundra in Gujarat by September 2011.

Around 65 per cent work on the unit has been completed. Erection of boiler pressure parts for the final three units and work on chimneys and 400-kV switch yard are proceeding as per schedule. Structural fabrication of external coal handling system is 85 per cent complete

The UMPP is being set up at a cost of Rs 17,000 crore. The project is funded on a 75:25 debt-to-equity ratio by a consortium of banks, including State Bank of India, International Finance Corporation, Asian Development Bank, KEIC and K-Exim.

After the commissioning of the first unit in September, the company hopes to commission the remaining four units at an interval of every four months.