Illustrative image – not actual.The first set of 12 private trains will be introduced in 2023, followed by 45 more in FY24.
The Indian Railways plans to roll out all 151 such train services by 2027. In a formal kick-start to its plans to allow private entities to operate passenger trains on its network, the Railways earlier in July 2020 invited proposals from companies to run 151 modern passenger trains on 109 pairs of routes across the country.
The project will entail a private sector investment of about Rs 30,000 crore.
As part of the plan for private trains, the Railways has planned to introduce 12 trains in 2022-23, 45 in 2023-2024, 50 in 2025-26 and 44 more in 2026-27 taking the total number of trains to 151 by the end of FY27.
The request for qualification (RfQ), which was floated on 8 July 2020, is likely to be finalised by November 2020. The financial bids will be opened by March 2021 and selection of bidders is planned by 31 April 2021.
Seventy percent of the private trains will be manufactured in India which will be designed for a maximum speed of 160 km per hour.
There will be a reduction in journey time by around 10-15 percent at 130 km per hour and around 30 percent at 160 km per hour. The running time taken by a train will be comparable to or faster than the fastest train of the Indian Railways operating in the respective route.
The private player will pay the railways fixed haulage charges, energy charges as per actual consumption and a share in gross revenue determined through a transparent bidding process.
The Railways is expected to receive total haulage charges of around Rs 3,000 crore per annum from operation of these 151 trains. These trains will be operated by the driver and guard of the Indian Railways.
The operation and maintenance of these trains will be governed by standards, specifications and requirements by the Indian Railways.
The operation of the trains by the private entity will conform to the key performance indicators like punctuality (95 percent), reliability (not more than one failure for one lakh km of travel), upkeep of trains and other necessities.
The Railways has also pre-specified penalties which will be recovered from private players for failure to meet the prescribed performance standards and outcomes. Similarly, penalties will be pre-specified in the concession agreement for failure on part of the Railways.
The Indian Railways plans to roll out all 151 such train services by 2027. In a formal kick-start to its plans to allow private entities to operate passenger trains on its network, the Railways earlier in July 2020 invited proposals from companies to run 151 modern passenger trains on 109 pairs of routes across the country.
The project will entail a private sector investment of about Rs 30,000 crore.
As part of the plan for private trains, the Railways has planned to introduce 12 trains in 2022-23, 45 in 2023-2024, 50 in 2025-26 and 44 more in 2026-27 taking the total number of trains to 151 by the end of FY27.
The request for qualification (RfQ), which was floated on 8 July 2020, is likely to be finalised by November 2020. The financial bids will be opened by March 2021 and selection of bidders is planned by 31 April 2021.
Seventy percent of the private trains will be manufactured in India which will be designed for a maximum speed of 160 km per hour.
There will be a reduction in journey time by around 10-15 percent at 130 km per hour and around 30 percent at 160 km per hour. The running time taken by a train will be comparable to or faster than the fastest train of the Indian Railways operating in the respective route.
The private player will pay the railways fixed haulage charges, energy charges as per actual consumption and a share in gross revenue determined through a transparent bidding process.
The Railways is expected to receive total haulage charges of around Rs 3,000 crore per annum from operation of these 151 trains. These trains will be operated by the driver and guard of the Indian Railways.
The operation and maintenance of these trains will be governed by standards, specifications and requirements by the Indian Railways.
The operation of the trains by the private entity will conform to the key performance indicators like punctuality (95 percent), reliability (not more than one failure for one lakh km of travel), upkeep of trains and other necessities.
The Railways has also pre-specified penalties which will be recovered from private players for failure to meet the prescribed performance standards and outcomes. Similarly, penalties will be pre-specified in the concession agreement for failure on part of the Railways.