The works on the Surya Regional Water Supply Scheme in the extended western suburbs of the Mumbai Metropolitan Region (MMR) is in near-completion stage.
Portable water will be provided to the Vasai-Virar City Municipal Corporation (VVCMC), once the project is complete. Under the second phase, 218 MLD clean drinking water will be supplied to the Mira-Bhayandar Municipal Corporation (MBMC).
Mumbai Metropolitan Region Development Authority (MMRDA) is constructing a 403 MLD water treatment plant wherein the work on the intake structure has achieved 98 percent completion and close to 94 percent work on the water treatment plant is completed. Further stages of testing, trial run and commissioning procedures will be initiated in the coming weeks.
A total of 88 km of pipeline has been laid between the Surya River (between Palghar-Manor) and Vasai-Virar municipality jurisdiction. Tunnelling work in Mendhwankhind is completed, while the work on Tungareshwar tunnelling is underway. Overall, 95 percent of phase-1 and 82 percent of the entire project has been completed.
The plan is to ensure a supply of 185 MLD in March 2023.