First phase of Parandur airport to cost Rs 13.8K-crIllustrative image – not actual.

The first phase of the proposed greenfield airport at Parandur near Chennai in Tamil Nadu will cost Rs 13,854 crore. The entire project, which will be implemented over four phases, will cost Rs 29,143 crore, as per a pre-feasibility report prepared by Louis Berger International for Tamil Nadu Industrial Development Corporation (TIDCO).

The report envisages the first phase of the airport to become operational by 2029, and would cater to 20 million passengers per year. TIDCO has planned to resume work by end of next year after acquiring land for the project. A total of 5,369 acres (2172.73 hectares) is required for the project.

As per the revenue records of the land required for the airport, one-fourth consists of waterbodies (576.74 hectares). Of the remaining land parcels required, 47.6 percent is irrigated agriculture land (1031 hectares), 16.35 percent is dry farm land (355 hectares), 1.36 percent is road, and 7.96 percent is government or poramboke land (173 hectares), with 0.32 percent as built-up area (6.96 hectares). The land price will be calculated as per the circle value of the respective villages fixed by the registration department.

The estimated budget for resettlement action plan for the project will include land acquisition cost and cost of the structures to be demolished, and a contingency plan. 

According to the report, the second phase of construction will be from January 2033 to December 2035, catering to another 30 million passengers per year, while the third phase will be implemented from January 2041 to December 2042, catering to another 20 million.

The fourth phase is earmarked from January 2044 till December 2046, which would add another 30 million passengers. A total of about 8,000 construction workers will be deployed during the construction phase temporarily.