First monorail train to arrive in Mumbai soonIllustrative image – not actual.

The MMRDA is likely to receive the delivery of its first train for monorail project in September 2010. MMRDA has ordered for six such trains for Phase I of the project.

The project costing Rs 3,000-crore will ease the transportation woes of at least 15-18 lakh commuters. The project is on fast track and the first phase of about 8.9 km between Chembur and Wadala will be ready soon.

Around 60 per cent work of the first phase is completed and Phase II from Wadala to Sant Gadge Maharaj Chowk also will be ready by mid-2011. The completed works include, civil works, rolling stock, signaling & communication systems and, electrical works etc.