Kasturi Park Metro station on Malad Link Road in Mumbai will be the first Metro station structure to be ready.
The project is being undertaken by the Delhi Metro Rail Corporation (DMRC) and is a part of the Dahisar-DN Nagar Metro-2A corridor.
The metro station structure will be ready before June 2018. Other amenities such as the staircase, toilets, flooring, control room and station master room will be completed by 2018 end.
The construction work on three Metro corridors, namely Dahisar-DN Nagar Metro-2A, Dahisar East-Andheri East Metro-7 and Colaba-Bandra-Seepz Metro-3 underground corridor began in 2016.
DMRC is constructing Metro-2A corridor of 18 km on behalf of the Mumbai Metropolitan Region Development Authority (MMRDA). It aims to complete construction on structures of at least 10 of the 17 Metro stations before the end of monsoon.
Metro-2A corridor is expected to be made operational for the general public by 2020.