Mumbai Metropolitan Region Development Authority (MMRDA) has achieved another milestone by installing the first of five composite steel girder spans. The 40-metre-long span, weighing around 130 tonnes, connects the Mumbai Trans Harbour Link (MTHL) Package-1 with the Eastern Freeway at two levels.
The interchange bridge is mainly composed of segmental box girder and cast-in-situ concrete decks of mostly 40 mtr spans, except for steel composite spans across the Eastern freeway.
The Mumbai Trans Harbour Link (MTHL) is a six-lane road bridge that connects Sewri in Mumbai to Chirle in Navi Mumbai. When completed, it will be the longest sea bridge in India. For execution, MTHL is divided into three construction packages, the first of which includes a 10.38 km of bridge section spanning across Mumbai Bay and Sewri Interchange.
The 10.38 km of Package-1 is broadly divided into three zones: the marine zone, which is about 5.755 km long, the intertidal zone, which is about 4.130 km long and the land zone (Sewri Interchange). In total, there are eight ramps in the land zone that connect the MTHL main bridge with the existing Eastern Freeway (4 ramps), the proposed Sewri Worli Elevated bridge (2 ramps) and the MbPT road below the Eastern freeway (2 ramps).
The bridge is about 22 km long, with 16.5 km of sea bridge and 5.5 km of viaducts on land at either end.