Illustrative image – not actual.The scope of the brownfield project worth Rs 50 crore also includes expansion of distillery capacity from 60 klpd to 150 klpd and co-generation power unit capacity from 38 MW to 49 MW.
The company has obtained the terms of reference (ToR) for the proposed project in 2017 and after a long wait, environment clearance (EC) was issued in 2018.
As reported to Projects Today, the company is currently engaged in the process of achieving financial closure. Once it is achieved, work on the project would commence by March 2019, according to the promoter.
The Vasantdada Sugar Institute is the consultant and S D Engineering Services is the Environmental Impact Assessment (EIA) Consultant in-charge for the project.