Illustrative image – not actual.The O P Jindal Group expects to achieve financial closure for its proposed Rs.9,500 crore aluminium project near Visakhapatnam in Andhra Pradesh in the next three to six months.
The project involves a 1.5 million tpa alumina refinery and a 2.5 lakh tpa aluminium smelter . Energy requirements would be meet through a 650 MW captive power plant. The raw material - bauxite ore - would be sourced from the AP Mineral Development Corporation (APMDC), which would mine the bauxite independently.
The company expects to receive all the clearances for the aluminium project, including bauxite mining and environmental, in the next 3-6 months. The project would be implemented in two phases, involving a time frame of two years each. The first phase is expected to involve a capital expenditure of around Rs 3,000 crore.
Phase I would be implemented with the help of internal accruals and funds from the financial institutions and banks. For Phase II, the company might consider raising funds from the capital market.
An independent public limited company, tentatively called JSW Aluminium, will be floated for implementation of the aluminium project. In the joint venture for bauxite mining, APMDC would hold 51 per cent equity, while JSW would have 49 per cent. The equity holdings pattern for the aluminium company would be worked out later.