Illustrative image – not actual.GMR Infrastructure has attained financial closure for the 73-km Tindivanam-Ulundurpet highway segment on NH-45 in Tamil Nadu that is part of NHDP (Phase III-A).
The Rs.795 crore project was awarded to GMR on a 20-year BOT basis, the concession agreement for which was signed in April 2006. The project is scheduled for completion within 18 months. It may be mentioned that this project involved a negative grant of around Rs.150 crore.
GMR will be raising Rs.596.25 crore as debt through a loan syndicated by ICICI Bank with other lending members being Andhra Bank, Bank of India, Bank of Baroda, Central Ban of India, Canara Bank, IDBI, IIFCL, Punjab National Bank and Union Bank of India. The remaining Rs.198.25 crore will come as equity.
The Tindivanam-Ulundurpet is part of the 210-km Tindivanam-Tiruchi (Trichy) four-laning project on NH-45 in Tamil Nadu that is being implemented in three distinct packages. The other two packages are being implemented by consortia led by IJM Corporation and Indu Projects.
Related Links:
Project
profile