Financial closure for Krishnapatnam project by MayIllustrative image – not actual.

NCC, formerly Nagarjuna Construction Company, is likely to achieve financial closure for its power project in Andhra Pradesh, by May 2011. The company is setting up a 1,320 MW thermal power project in partnership with Gayatri Projects at Krishnapatnam at an investment of Rs 7,000 crore.

PFC and REC have agreed to infuse Rs 3,200 crore, which is part of the Rs 5,200 crore debt portion, and for the rest, NCC is holding discussions with the State Bank of India and the ICICI Bank.

About 830 acre has been acquired for the project, and all mandatory clearances, including environment have been obtained.