Financial closure for Dhamra Port delayedIllustrative image – not actual.

Financial closure for the Dhamra Port project is now likely by November 2006, as against end-September 2006 earlier felt. The project has been facing some environmental concerns from turtle conservationists. Physical work on the project is scheduled to start once the financial closure milestone is reached.

Dhamra Port Co Ltd -- an equal joint venture between Larsen & Toubro and Tata Steel -- is implementing the project. Phase I of the project, expected to commission by April 2009, will see an investment of Rs.2,400 crore. In this phase, two deep draught berths for dry bulk and one berth for clean cargo will be developed.

In its entirety, the project will see 13 berths capable of handling more than 80 million tonnes of dry bulk, break bulk, liquid bulk and containerized cargo. The port will have a draught of 18m and will be equipped to handle cape size vessels of up to 1.8 lakh dwt.

Also See:

Financial closure for Dhamra Port by end-September 2006 (29-Jul-06)

Related Links:
Project profile

← All latest storiesBack to top →