Illustrative image – not actual.The financial closure for as many as 13 power projects, which received techno-economic clearance, has been held up. The financial constraints of the respective SEBs is among the main reasons for the delay.
The projects are listed below:
|
Power Project |
Cap. (MW) |
Promoter |
Location, State |
Reason for delay in
financial closure |
|
Jamnagar Power Project |
500 |
Reliance Jamnagar Power Co.
Ltd. |
Jamnagar, Gujarat |
Funds constraints of GEB |
|
Nagarjuna Power Project |
1,015 |
Nagarjuna Power Co. Ltd. |
Mangalore, Karnataka |
PPA not approved by State
government |
|
Kannur Power Project |
513 |
Kannur Power Projects Ltd. |
Kannur, Kerala |
Lack of escrow cover |
|
Vembar Power Project |
1,873 |
Indian Power Projects Ltd. |
Tuticorin, Tamil Nadu |
TNEB unable to absorb power |
|
Cuddalore Power Project |
1,320 |
Cuddalore Power Co. Ltd. |
Cuddalore, Tamil Nadu |
TNEB unable to absorb power |
|
Vemagiri Power Project |
520 (Rev.) |
Vemagiri Power Generation
Ltd. |
East Godavari, Andhra Pradesh |
TEC for capacity revision
from 492 MW |
|
Ib Valley Power Project |
500 |
IB Valley Power Pvt. Ltd. |
Jharsuguda, Orissa |
Non-issuance of government
guarantees |
|
Duburi Power Project |
500 |
Kalinga Power Corpn. Ltd. |
Cuttack, Orissa |
Non-issuance of government
guarantees |
|
Srinagar Hydel Power
Project |
330 |
Duncan North Hydro Power
Co. |
Pauri Garhwal, Uttaranchal |
Funds constraints of
Uttaranchal SEB |
|
Dhamwari Sunda Hydel Power
Proj. |
70 |
Dhamwari Power Co. Pvt.
Ltd. |
Shimla. Himachal Pradesh |
Funds constraints of HPSEB |
|
Allain Duhangan Hydel Power Proj. |
192 |
Rajasthan Spinning & Weaving Mills Ltd. |
Kullu, Himachal Pradesh |
Funds constraints of HPSEB |
|
Gouripower Power Project |
150 |
Gouripore Power Co. Ltd. |
24 Parganas (N), West Bengal |
Funds constraints of WBSEB |
|
Kaniminke Power Project |
107.6 |
Peenya Power Co. Ltd. |
Bangalore, Karnataka |
Lack of escrow cover |