Financial closure by September for GVK's Punjab projectIllustrative image – not actual.

GVK Power & Infrastructure Ltd (GVKPIL) is likely to achieve financial closure for its Rs 3,000 crore Goindwal Sahib project at Taran Taran in Punjab by September 2009.

GVKPIL is known to have a term sheet for debt equity of 75:25 and is currently holding talks with financial institutions for raising the funds. The company intends to complete the project within 39 months from the date of achieving financial closure.

The coal for the thermal plant is likely to be sourced from the captive mines in Tokisud North sub-block in Jharkhand.

The company has signed the Amended and Restated PPA with the Punjab State Electricity Board (PSEB) on 26 May 2009 for implementing the 2 x 270 MW coal based power project.