Financial closure achieved for Mundra UMPPIllustrative image – not actual.

On 24 April 2008, Tata Power Co announced the completion of signing of financial agreements for the 4,000 MW Ultra Mega Power Project (UMPP) at Mundra in Kachchh district of Gujarat, under the company's special purpose vehicle -Coastal Gujarat Power (CGPL).

A consortium of banks including leading multilateral agencies and Exim Banks are participating in the financing of the proposed project. The financing comprises of equity of Rs.4,250 crore, external commercial borrowings (ECB) of upto $1.8 billion and rupee loan of upto Rs.5,550 crore. The ECB's include The Export-Import Bank of Korea, International Finance Corporation, Korea Export Insurance Corporation, Asian Development Bank, BNP Paribas and rupee lenders include SBI (Lead bank for rupee lenders), India Infrastructure Finance Co, Housing & Urban Development Corporation, Oriental Bank of Commerce, Vijaya Bank, State Bank of Bikaner & Jaipur, State Bank of Hyderabad, State Bank of Travancore and State Bank of Indore. SBI Caps are the financial advisors and mandated lead arranger for rupee loans.

The cost of the project is estimated at Rs.17,000 crore. The project consists of five units, each of 800 MW, which will generate saleable power of 3,800 MW to be supplied to five states namely Gujarat, Maharashtra, Rajasthan, Haryana and Punjab.

The site preparatory works are in progress and orders for all major equipments have been placed. The company has signed the contract for complete boiler island scope on EPC basis with Doosan Heavy Industries & Construction Co, Korea and contract for supply of steam turbine generators with Toshiba Corporation. The project has been comprehensively covered by a seamless insurance cover by Oriental Insurance Co.

The first of the five units will be commissioned in September 2011 and the entire plant is expected to be commissioned by end of 2012.