Financial closure achieved for 330 MW Shrinagar hydroelectric projectIllustrative image – not actual.

Alakananda Hydro Power Co has achieved financial closure for its (4 x 82.5 MW) 330 MW Shrinagar hydroelectric project in Pauri Garhwal district of Uttarakhand.  

The capital cost of the project is estimated to be Rs.2,069 crore, which will be funded through a debt equity ratio of 80:20. The debt component of Rs.1,655 crore is funded by infusion of Rs.1,494 crore and Rs.161 crore as dollar component. The project will have equity of Rs.414 crore.

Alakananda Hydro Power Co (AHPCL) is implementing the project in pursuant to an implementation agreement signed in February 2006 with the Uttar Pradesh and Uttarakhand Governments. The power purchase agreement (PPA) for the project was signed in June 2006 with Uttar Pradesh Power Corporation (UPPCL), valid for a period of 30 years. As per the PPA, UPPCL has agreed to purchase 88 per cent of the energy generated by the Shrinagar Power Project. The remaining 12 per cent will be supplied free to Uttarakhand.

Also See:

Uttar Pradesh signs PPAs with three IPPs (13-Nov-06)

Related Links:
Project profile

← All latest storiesBack to top →