Financial bids to be opened for Dharavi slum redevelopment projectIllustrative image – not actual.

Financial bids for Dharavi slum redevelopment project, which had been in the pipeline since 2004, will be opened on 16 January 2019.

In a pre-bid meeting, 15 to 20 top developers from across the country participated. However, only two bidders have submitted their bids for the ambitious redevelopment project. One bid was received from a Dubai-based firm, Seclink Group while the other was from the Adani Group.

On 23 November 2018, the Slum Rehabilitation Authority floated global tenders for the Dharavi redevelopment project. The Maharashtra state government decided to redevelop Dharavi as a special project as an integrated planned township. The estimated cost of the project is Rs 20,000 crore.

The government had notified lands admeasuring around 240 ha as the Dharavi Notified area and appointed the Slum Rehabilitation Authority as the Special Planning Authority.

The government plans to extend various concessions to facilitate speedy completion of the project. The selected lead partner will set up a SPV with 80 per cent equity (Rs 400 crore), the government will hold 20 percent equity (Rs 100 crore). Under the SPV, free housing for eligible slumdwellers and occupants including amenities and infrastructure will have to be constructed as per the bid document.

The proposed completion period for the construction of rehab, renewal, amenities and infrastructure is seven years from the signing of the development agreement.

 