Illustrative image – not actual.The newly-formed special purpose vehicle (SPV), the Uttar Pradesh Metro Rail Corporation (UPMRC), has given approval to its final detailed project report (DPR) for East-West (E-W) Corridor. The corridor is part of Phase-II of the Lucknow Metro Rail project.
After this, the DPR will be presented before the state government and the Public Investment Board (PIB) for clearance and then will finally go to the Union Cabinet for approval.
As per the approved DPR, the total corridor length will be 11.2 km with 4.3 km elevated section and 6.9 km underground stretch from Vasantkunj to Charbagh.
Charbagh will serve as the interchange junction between the North-South (N-S) and East-West (E-W) corridor. E-W stretch will have seven underground Metro stations and five elevated ones.
As per the DPR, E-W corridor will have just three-coach trains and small stations unlike N-S Corridor which has six-coach trains and relatively big stations.
The East-West corridor is likely to be complete by September 2023, provided it gets approval from the Centre by 2019. The daily ridership is likely to be 2,13,440.
The initial DPR had pegged total construction cost at around Rs 5,500 crore, whereas the revised one has hiked it to Rs 6,500 crore.
The elevated stations of the corridor will be Vasantkunj, Musabagh, Sarfarazganj, Balaganj and Thakurganj, while the underground stations will be Nawajganj, Medical Chouraha, City Railway Station, Pandeyganj, Aminabad and Gautam Buddha Marg.
The Lucknow Metro is scheduled to commission the entire 23 km of Phase-I corridor from Chaudhary Charan Singh Airport to Munshipulia by April 2019.