Illustrative image – not actual.The expert group to be set up by financial institutions (FIs) to determine time and cost overruns for around 20-25 high-cost projects under implementation, is expected to decide the dates of completion on a project-by-project basis and submit details by 30 March 2002.
Most of these projects are in the steel and oil refining sectors and have undergone substantial cost and time overruns with funding in excess of Rs.25,000 crore and technically, the value of these assets has been impaired. Generically, these projects will include new-generation steel companies and refineries, particularly on the west coast.
The move follows issuance of new norms pertaining to the treatment of loans in the case of time overrun projects by the Reserve Bank of India (RBI), on 7 February 2002. It is expected that formal documentation of the date of completion of these projects will enable FIs to classify assets - standard or otherwise.
The expert committee will decide on the date of completion of projects still under implementation and wherein the same has not been formally documented. The date so fixed - spillover of more than two years - will decide which of these assets attract sub-standard classification norms.
RBI had noted that instances have been observed where despite substantial time overrun in the projects under implementation, the underlying loan assets have remained classified in the standard category merely because the project continued to be under implementation. Recognising that unduly long time overrun in a project adversely affected its viability and the quality of the asset deteriorated, a need has been felt to evolve an objective and definite time-frame for completion of projects so as to ensure that the loan assets relating to projects under implementation are appropriately classified and asset quality correctly reflected.
The RBI has stated that the date of completion should be clearly spelt out at the time of financial closure, in case of projects to be financed by the FIs in future. In such cases, if the date of commencement of commercial production extends beyond six months after date of completion as originally envisaged at the time of initial financial closure of the project, the account should be treated as a sub-standard asset.
Projects will now be grouped into three categories - projects wherein financial closure had been achieved and formally documented; projects with original project cost of Rs.100 crore or more; projects with original project cost of less than Rs.100 crore.
It might be recalled that in an RBI circular dated 28 March 1994, a time overrun of up to 50 per cent is permitted before downgrading to sub-standard. Further, in an RBI circular dated 24 June 1996, a one-time refixing of the time-period is allowed with the approval of the board even if the time overrun is more than 50 per cent. In that case, the asset could be treated as standard till the time so refixed by the board. The RBI has now for each of the three categories, set a date by which the project ought to be completed and the classification of the underlying loan asset would be determined in the following manner.
In category I - infrastructure projects or large value manufacturing projects financed after 1997 - the two years’ time period should be counted from the date of completion of the project, as envisaged at the time of original financial closure. In category-2, projects sanctioned prior to 1997 - with the date of financial closure not been formally documented - an independent group may be constituted with the experts from the lending institutions as well as outside experts in the field. The group, based on all material and relevant facts and circumstances, would decide the date, on a project-by-project basis, which would be the deemed date of completion of the project. In category-3, projects sanctioned prior to 1997 - the date of commencement of commercial production would be deemed to be the date exactly two years after the date of completion of the project, as originally envisaged as the time of sanction.