Illustrative image – not actual.The feasibility report of NTPC's Kayamkulam project is ready, according to information tabled in the Rajya Sabha recently. It is further learnt that several clearances are already in place while others are in progress.
Petronet LNG would be supplying 2.1 million tpa of LNG (around 8.4 mmscmd of gas) to both the existing 350 MW plant and the 1,950 MW expansion project.
Land is already available and in-principle commitment of water supply has been obtained from the state government. Besides, Airports Authority of India has given aviation clearance and the NOC from Kerala State Pollution Control Board has already been obtained.
NTPC would approach the Union ministry for environment & forests for clearance, after the fuel supply agreement is signed.
NTPC's Kayamkulam expansion project involves setting up of 1,950 MW of gas-based power capacity. The project costing Rs.7,584 crore represents Stage II of the power plant. Stage I comprising a 350 MW power unit (coal-based) that is already in operation. Power from Stage II will be supplied to states and Union territories in the southern region. The project is scheduled to commission in the XI Plan period (2012-17).